Site visit to the Garda Cycle Path, Riva del Garda
Today, the visit to the construction works of Functional Unit 1.2 of the Garda Cycle Path took place, as announced on March 26th at the Riva del Garda City Council. The Mayor, councilors, and municipal council members were accompanied by the President of the Province, the extraordinary commissioner for the project Francesco Misdaris, the general manager of the Department of Infrastructure Luciano Martorano, and the geologist Claudio Valle, consultant to Commissioner Misdaris for the Cycle Path.
During the site visit, the technical details of the project were explained. The different construction phases of the tunnels were observed, both the existing ones that have been reinforced and the new ones that have been built to mitigate the impact of large rocks. A section has been created to allow the passage of emergency vehicles, and the external facades of the tunnels are being camouflaged in various shades of gray to blend in with the surrounding rocks. Additionally, both the new and existing tunnels will be adorned with artistic decorations designed by architect Ferrari.
The current status of the Garda Cycle Path in the Trentino section is as follows:
– Functional Unit 1.2: Ponale Underpass-Orione Tunnel: works amounting to 9.6 million euros, completion of works in July 2025, executed works amounting to 2.8 million euros.
– Functional Unit 2: Orione Tunnel-Ponale Mouth: works amounting to 10.3 million euros, completion in August 2026.
– Functional Unit 3.1: Border with Lombardy-Limniadi Tunnel: works amounting to 2.6 million euros, completion in September 2024.
– Functional Unit 3.2: Limniadi Tunnel-Gola Location: works amounting to 7 million euros, completion in March 2026.
– Functional Unit 3.3: Gola Location-Titani Tunnel: works amounting to 5.8 million euros, completion in February 2026.
– Functional Unit 3.4: Titani Tunnel-Ponale Mouth: works amounting to 24 million euros, completion in December 2026.
– Additional Functional Unit (UF) 3.5: Safety measures for the rock walls above the entire UF3 section: works amounting to 5.3 million euros, completion in November 2025.
– UF18: Torbole Center-Riva del Garda: completion in June 2026, total works amounting to €4.2M from Pnrr funds.
– UF19: Torbole-Nago: Completion in December.