Works on the SP572 in Manerba del Garda are nearing completion, according to the Province of Brescia. The works on the outer surface of the structure are almost finished, but a second intervention has been planned to strengthen the bridge’s structural elements.
To ensure normal city traffic during the installation of the new road surface, a one-way alternating traffic system will be implemented with traffic controllers. This will allow vehicles to continue circulating without significant disruptions.
The total cost of the works amounts to €640,000 and will be financed through various funds. In particular, €320,000 comes from Regional Law 24/2019, another €270,000 is funded by the Province of Brescia, and €50,000 will be covered by the M.E.F. 1/2020 Ponti bacino del Po funds.